On 27 October 2026, a court settlement was concluded between PKP Polskie Linie Kolejowe S.A., the City of Łódź and PKP S.A., and the consortium of contractors for the Łódź Fabryczna project: TORPOL S.A., WEBUILD S.p.A. (formerly ASTALDI S.p.A.), INTERCOR sp. z o.o. and Przedsiębiorstwo Budowy Dróg i Mostów sp. z o.o. (in restructuring).
The settlement covers two court proceedings concerning claims for additional works and the costs of extending the contract completion period. The total value of the agreed settlement is approximately PLN 71.4 million gross.
Wierzbicki&Co represented PKP Polskie Linie Kolejowe S.A. in the long-standing dispute and took part in the negotiations that led to its amicable resolution. The matter was led by Iwona Nogaj, advocate, with the support of Przemysław Wierzbicki, advocate.
The settlement demonstrates that even the most complex infrastructure disputes can be resolved through constructive dialogue and compromise.
Press releases (PL version):
Koniec wieloletniego sporu o Łódź Fabryczną. Ugoda na 71,4 mln zł – Kolejowy Portal
Łódź Fabryczna: W końcu jest ugoda Torpolu z inwestorami – Rynek Infrastruktury